Pressenachrichten - News from the building site 22.10.2009
News from the building site 22.10.2009
The builders are preparing approximately one quarter of the building site to be paved on the right side seen from Májová Street. In fact it is the section from Terea to the restaurant Dejavu near Prior, where all construction layers and cables were laid and planting baskets were set. The work continues by setting drainage canal and curbs, and installation of roof cleaners and English yards covers will be done as well.