« Mai 2012 »
Mo Di Mi Do Fr Sa So
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31
virtuální prohlídka
Pěší zóna Cheb on Facebook

Pressenachrichten - News from the building site 8.10.2009

News from the building site 8.10.2009

The second stage of the pedestrian zone reconstruction is in the same way as the first one realised so that always one side of the street is through. Due to worse weather the work continues in smaller sections. On the right side  (seen from Májová Street) laying rain drainage and setting planting baskets continues. Approximately in one third of the construction site all construction layers are finished, cables for public lighting, Internet and electric cables are layed. Construction layers and planting baskets assembling also on the left side is being done, which is necessary for laying pavement on the right side.

zurück

_TOP druck