Period I: January 2008 - August 2009
Includes the preparation and realization project stage:
1) Preparation stage (January2008 - February 2009) is connected with all preparations demanded for the future project realization, which includes:
• working out the project documentation for the given grade of managing
• working out the grant application including obligatory supplements
• selection procedure (construction suppliers, publicity, artwork contractors competition)
2) Realization stage (from March 2009) starts in stage I, continues in stage II and III until the project´s end in July 2011.
Parts of the project:
• Construction work (the most significant financial volume) - in stage I it concerns pedestrian zone reconstruction in the section Májová Street to Evropská Sstreet.
• Publicity
• Administration and monitoring the period
Period II: September 2009 - June 2010
• Construction work (the most significant financial volume) - solves pedestrian zone reconstruction in the section King George Square (Náměstí Krále Jiřího) to Májová Street section, part of which is artwork in form of demogram.
• Publicity
• Administration and monitoring the period
Period III: July 2010 - December 2010
• Construction work (the most significant financial volume) - solution of Májová Street and Valdštejnova Street crossroad
• Publicity
• Administration and monitoring the period
• Final evaluation of the whole action
• Elaborating the final payment and monitoring report
Physical project (construction) termination is planned on 31.10.2010, the whole project termination (administrative) is on 31.12. 2010.
| « | Mai 2012 | » | ||||
| Mo | Di | Mi | Do | Fr | Sa | So |
| 1 | 2 | 3 | 4 | 5 | 6 | |
| 7 | 8 | 9 | 10 | 11 | 12 | 13 |
| 14 | 15 | 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 | 26 | 27 |
| 28 | 29 | 30 | 31 | |||
Pěší zóna Cheb on Facebook