Description of time realization

Description of time realization

Period I: January 2008 - August 2009

Includes the preparation and realization project stage:

1) Preparation stage (January2008 - February 2009) is connected with all preparations demanded for the future project realization, which includes:

working out the project documentation for the given grade of managing
working out the grant application including obligatory supplements
selection procedure (construction suppliers, publicity, artwork contractors competition)


2) Realization stage (from March 2009) starts in stage I, continues in stage II and III until the project´s end in July 2011.

Parts of the project:

Construction work (the most significant financial volume) - in stage I it concerns pedestrian zone reconstruction in the section Májová Street to Evropská Sstreet.
Publicity
Administration and monitoring the period


Period II: September 2009 - June 2010
Construction work (the most significant financial volume) - solves pedestrian zone reconstruction in the section King George Square (Náměstí Krále Jiřího) to Májová Street section, part of which is artwork in form of demogram.
Publicity
Administration and monitoring the period


Period III:
July 2010 - December 2010

Construction work (the most significant financial volume) - solution of Májová Street and Valdštejnova Street crossroad
Publicity
Administration and monitoring the period
Final evaluation of the whole action
Elaborating the final payment and monitoring report


Physical project (construction) termination is planned on 31.10.2010, the whole project termination (administrative) is on 31.12. 2010.